BookMark:
The new BookMark is under way. Project completed in
Mar 06.
The new BookMark will be co-located inside the food court. Cost of project
estimated at $250K
Shoppette with gas & Car Care Center:
New Shoppette scheduled for construction in 2007. Will be co-located with
the Car Care Center. Cost of project estimated at $950K
Food Court:
Image upgrade. New counters for Anthony’s Pizza and Baskin Robbins along
with new tables and chairs, painting of the facility. Scheduled for summer
06. Cost of the project estimated at $200K
Main Store:
Complete reset of the entire main store is under review.
Currently renovation of Power Zone is taking place with new flooring,
fixtures and lighting. When new Shoppette is completed, the move of the main
store categories will move form the PXtra to the Main Store. No
target date.
Spangdahlem
| Chievres
| Bitburg
Home | Information | GM's Statement | Worldwide Locations
_^_
updated:
07/11/08
|