Projects Recently Completed:
  1. Shoppette /Gas, new construction –Jeb Stuart Status: complete Project Scope: 5,200 SF Shoppette, and 6 gas dispensers. Project start date: September 2006; Project completion date: July 2007.
  2. Logan Heights Add Gas to Shoppette- expansion. Status: Gas dispensers completed: Snack Ave addition (Jan 09)
Projects under Construction:
  1. Burger King/Popeye’s Dual Food, new construction: Scope: 5,600 SF dual food concepts. Project start date: Sept 2008; Project completion date: May 2009
  2. East Bliss #1 Mini-mall / gas/ food/ concessions- new construction Status: under construction. Project Scope: 16,000 SF Mini-Mall, food concepts, 8 gas dispensers with 3 food concepts: Subway, Burger King and Pizza Hut. Project start date: October 2007; Project completion date: December 2008.
  3. Bliss Day Spa: Project start date Nov 8; Project completion date TBD
Projects in Design:
  1. Blimpies at Bldg 1293 project start date Nov 08 ; Project completion date Jan 09
  2. Pizza Hut Delivery (located in the old Pizza pros building) Target Opening Feb 2009
  3. Cassidy Shoppette Subway Status: Design. Project start date: Jan 2009, Project completion date: May 2009
  4. East Bliss #2 Community Center Troop Mall. Status: design. Project scope: Troop mall, food court, concessions. Project start date: TBD. Project completion date: TBD
  5. East Bliss #4 Mini Mall (by IBCT area). Status: Design. Project start date: TBD. Project completion date: TBD

 

Future Projects Identified:
  1. East Bliss Firestone- Status: identified. Project start date: TBD. Project completion date: TBD.
  2. East Bliss Carwash- new construction. Status: identified. Project scope: Public Private Venture (PPV) wand and rollover carwash. Start date: TBD. Project completion date: TBD.
  3. Jeb Stuart Taco Bell w-drive thru Status: identified. Project start date: TBD. Project completion date: TBD.
  4. Main Post Burger King Upgrade. Status: identified. Project start date: TBD. Project completion date: TBD.
  5. East Bliss #6 Shoppette North. Status: identified. Project start date: TBD. Project completion date: TBD.
  6. Bliss Firestone identified. Project start date: TBD. Project completion date: TBD
  7. Blimpies at Special Troops. Project start date: TBD. Project completion date: TBD
  8. East Bliss #5 Shoppette replacement with additional gas dispensers project start date TBD: Project completion date TBD

updated: 11/20/2008